Pictures

August 2, 2011

 

Excavation of new addition.

 

Excavation of new addition.

 

Excavation of new addition as it attaches to current North end of Spencer Wing.

 

Future site of new Dietary Operation.

 

August 29, 2011

 

New addition dig site.

 

Basement level of new addition. Future location of Dietary Operation.

 

Excavation of new addition North of Spencer Wing.

 

Excavation site.

 

1962 Wing temporary wall. Behind this wall will be the new Dietary Operation.

 

1962 Wing doors marked for demolition.

 

September 1, 2011

 

Demolition of 1962 Wing.

 

1962 Wing framing.

 

September 9, 2011

 

1962 Wing demolition.

 

Excavation of new addition.

 

Excavation of new addition.

 

Excavation of new elevator shaft.

 

Framing for the 4th Floor apartments.

 

1962 Wing in the process of new roofing.

 

 

September 22, 2009

 

Placement of Rebar in new addition.

 

Replacement of Rebar in new addition.

 

Placement of Rebar in new addition.

 

Placement of Rebar in new addition.

 

1962 Wing new roof.

 

September 23, 2011

 

Pumping concrete into footings in new addition.

 

Pouring footings in new addition. Elevator shaft to the right.

 

Pouring footings in new addition. Elevator shaft to the right.

 

October 11, 2011

 

Pouring concrete walls for the basement of the new addition.

 

Pouring concrete walls for the basement of the new addition.

 

Pouring concrete walls for the basement of the new addition.

 

November 1, 2011

 

New concrete flooring of basement for new addition.

 

Old kitchen vent to be removed.

 

New showers for apartments arrived.

 

Placement of new shower in apartment.

 

November 10, 2011

 

Future Dietary storage area.

 

Rebar to start 2nd Floor.

 

Rebar to start 2nd Floor.

 

Rebar to start 2nd Floor.

 

November 21, 2011

 

2nd Floor getting ready for concrete to be poured.

 

1962 Wing framing in progress.

 

Crane lifting rebar to 2nd level.

 

Rebar for flooring on the next level.

 

Rebar for next level flooring.

 

November 22, 2011

 

Laying rebar on 2nd level floor.

 

Laying rebar on 2nd level floor.

 

Laying rebar on 2nd level floor.

 

November 30, 2011

 

Framing of the pillars for the 2nd Floor dining room.

 

Framing of the pillars for the 2nd Floor dining room.

 

December 2, 2011

 

Back filling.

 

Back filling.

 

December 19, 2011

 

Framing to pour concrete for the 2nd Floor dining room walls; this will be done in stages.

 

Framing to pour concrete for the 2nd Floor dining room walls; this will be done in stages.

 

The backfill is completed at this time. This will be the new patio area between the old and new building. More backfill will happen after the 2nd floor walls are done.

 

January 3, 2012

 

They have removed the forms after pouring the walls of the 2nd Floor and the elevator shaft.
Next they will be forming the next floor to be poured forming the ceiling of the 2nd Floor dining room/floor of the 3rd Floor dining room.

2nd Floor walls are up.

 

2nd Floor walls are up.

 

Elevator shaft.

 

January 18, 2012

 

The 3rd Floor is ready to pour concrete.

 

January 19, 2012

 

1962 Wing hallway. Windows have been removed and filled for the future delivery hallway.

 

January 23, 2012

 

4th Floor hallway where new apartments are located.

 

Kitchen area in the new 4th Floor apartments.

 

Bathroom in the new 4th Floor apartments.

 

Basement of the new addition (support beams will be removed).

 

February 24, 2012

 

2nd Floor patio area. Future kitchen to the left, 2nd Floor dining room windows to the right.

 

Future kitchen area.

 

Future 3rd Floor dining room - trusses going up.

 

New addition work.

 

Pouring footing for future loading dock.

 

Retaining wall for patio area.

 

March 5, 2012

Future loading dock.

 

Trusses going up for the top floor of the new dining room addition.